Activity
ID
Activity Name
Start
Finish
Rem
Dur.
Org Dur.
Biochemistry
08-Jun-09 A 01-Aug-12
776
812
Base Bid- Construction
08-Jun-09 A 23-Sep-11
553
589
Demo-Earthwork
08-Jun-09 A 10-Feb-10
138
174
Abatement
0
0
Demolition/ Selective Removals
27-Jul-09 A
28-Aug-09
24
50
1985 Building
24-Aug-09
28-Aug-09
5
5
1985 Cantilever Removal
24-Aug-09*
28-Aug-09
5
5
1956 Building
0
0
1906 Building
27-Jul-09 A
24-Aug-09
20
20
Vault Demolition
27-Jul-09 A
24-Aug-09
20
20
Steam Tunnel
0
0
1912/1937 Building
0
0
Earthwork
08-Jun-09 A 10-Feb-10
138
174
Site Utility
19-Nov-09
17-Dec-09
20
20
Sanitary Line - SAN MH-2 to SAN MH-5
19-Nov-09
17-Dec-09
20
20
Micropile
28-Jul-09
08-Sep-09
30
30
Micropile 1937 and 1912
28-Jul-09
08-Sep-09
30
30
Earth Retention & Excavation
08-Jun-09 A 28-Dec-09
107
143
North Tower
08-Jun-09 A 12-Aug-09
11
46
Earth Retention/ Excavation
08-Jun-09 A 12-Aug-09
11
46
Investigate and Remediate Water Issue- NE corner
08-Jun-09 A 19-Jun-09 A
0
10
Complete Retention and Mass Excavation
17-Jun-09 A 10-Aug-09
10
10
Subgrade Dewatering
18-Jun-09 A 12-Aug-09
0
1
South Building
21-Dec-09
28-Dec-09
5
5
Excavation
21-Dec-09
28-Dec-09
5
5
Backfill
15-Oct-09
10-Feb-10
82
82
Backfill to 79'-4" - North Tower- West Half
15-Oct-09
21-Oct-09
5
5
Backfill to 79'-4" - North Tower- East Half
29-Oct-09
04-Nov-09
5
5
Backfill to 100' - North Tower- West Half
14-Dec-09
18-Dec-09
5
5
Backfil to 100'- North Tower- East Half
04-Feb-10
10-Feb-10
5
5
Footing and Foundations- North Tower
12-Aug-09
12-Oct-09
43
43
Mat Foundation- Complete Rebar Install
12-Aug-09
20-Aug-09
7
7
Mat Foundation- Pour
21-Aug-09
21-Aug-09
1
1
Vertical Work- West Half
24-Aug-09
21-Sep-09
20
20
Vertical Work- East Half
22-Sep-09
12-Oct-09
15
15
Remainder
18-Sep-09
23-Sep-11
516
516
North Tower
22-Sep-09
19-Jan-11
340
340
Structure- North Tower
22-Sep-09
24-Jun-10
194
194
Basement-79'-4"
22-Sep-09
03-Dec-09
52
52
West
22-Sep-09
18-Nov-09
42
42
Deck and Pan Install
22-Sep-09
05-Oct-09
10
10
Rebar/ MEP Rough
29-Sep-09
12-Oct-09
10
10
EdgeForm- Close Up Deck
13-Oct-