Exam1pass
Easiest way to pass IT exams
Exam1pass Help You Pass Any IT Exam
http://www.exam1pass.com
Exam
: Microsoft 70-632
Title
: Pro: Microsoft Desktop
Support Consument
Version : Demo
Exam1pass
Easiest way to pass IT exams
Exam1pass Help You Pass Any IT Exam
http://www.exam1pass.com
1. You create a large project plan in Microsoft Office Project Standard 2007. Immediately before an
important status meeting, the project sponsor requests that you display the Work Breakdown Structure
(WBS) numbers. You have not customized the WBS code.
You need to display the WBS numbers as quickly as possible.
What should you do?
A. Enter the WBS numbers as part of the task names.
B. Change project options to show the outline number.
C. Refer to the ID field in a task table that you are using.
D. Insert the Unique ID field in a task table that you are using.
Answer: B
2. You are creating a project management methodology. You document project management procedures
and create specialized project management process templates.
You need to apply the processes in the context of Microsoft Office Project Standard 2007.
What should you do first?
A. Create a Project Guide.
B. Display the Task Drivers pane.
C. Display the Hyperlinks column.
D. Display the Microsoft Office Online Web site.
Answer: A
3. You are using a project plan created by another person as an example of how to create a project in
Microsoft Office Project Standard 2007. However, you do not want the original authors name to be
associated with your project plan.
You need to remove the original project plan author's name from the project plan.
What should you do?
A. Increase the macro security level to High.
B. Delete the user name from the program options.
C. Remove the authors resource from the resource pool.
D. Turn on the removal of information from the file properties.
Answer: D
4. You are managing a project schedule in Microsoft Office Project Standard 2007. You create 100 new
tasks in the project plan. Each task has a duration of 5 days, which you indicate by entering