SECTION 01323
CONSTRUCTION STATUS REPORTS
NTS: OPTION 1 (WW) AND OPTION 2 (MF) (07/01/2001)
1.1
THE REQUIREMENT
A.
Weekly Status Report
During the construction phase of the Work, the CONTRACTOR shall submit
weekly written status reports to the ENGINEER and the INSPECTOR. The
report shall contain a record of inspections and tests, not performed by CITY
forces, for all Work accomplished subsequent to the previous report and shall
include the following information:
1.
Type of work under way during the time frame of the report (e.g.,
earthwork,
concrete work,
structural
steel erection, equipment
manufacturing, component installation).
2.
Inspections and tests, and location of inspections and tests that were
made.
3.
Results of inspections.
4.
Reports of tests performed, including those specified, with the results of
the tests, and acceptance criteria, including failures and remedial action
to be taken. Test results, including all computations, shall be attached to
the report form. Where test results cannot be completed by the time the
report is submitted, a notation shall be made that the test was performed,
including the approximate expected date that test results will be reported.
5.
Report of any nonconforming items/activities. Nonconformance report
forms designed solely for this purpose shall be utilized.
6.
Results of inspections of material and equipment done upon their arrival
at the Jobsite and prior to their incorporation into the Work. This
includes, but is not limited to, compliance with approved submittals,
damage, and proper storage requirements.
7.
Offsite quality control ac