BROOKHAVEN SCIENCE ASSOCIATES
NSLS-II Update
Steve Dierker
Associate Laboratory Director for Light Sources
NSLS-II Project Director
November 13, 2008
2
BROOKHAVEN SCIENCE ASSOCIATES
Key Project Milestones
Aug 2005
CD-0, Approve Mission Need
(Complete)
Jul 2007
CD-1, Approve Alternative Selection and Cost Range
(Complete)
Jan 2008
CD-2, Approve Performance Baseline
(Complete)
Dec 2008
CD-3, Approve Start of Construction
Feb 2009
Contract Award for Ring Building
Aug 2009
Contract Award for Storage Ring Magnets
Mar 2010
Contract Award for Booster System
Feb 2011
1st Pentant Ring Building Beneficial Occupancy; Begin Accelerator Installation
Feb 2012
Beneficial Occupancy of Experimental Floor
Oct 2013
Start Accelerator Commissioning
Jun 2014
Early Project Completion; Ring Available to Beamlines
Jun 2015
CD-4, Approve Start of Operations
3
BROOKHAVEN SCIENCE ASSOCIATES
Great Progress
Light Sources Directorate Picnic
4
BROOKHAVEN SCIENCE ASSOCIATES
Final Design Plan
• Provides for a phased completion of the final designs:
• ensures designs are sufficiently mature to start procurement & construction
• enables most cost-effective construction schedule
• maximizes the technical capabilities
• Projected design % complete based on value of NSLS-II subsystems
• 74% complete at CD-3 w/ technical risk related to Key Performance
Parameters retired
Level 2 System
Value ($M)
Design Goal
at CD-3
Actual %
Complete at CD-3
Total Level 2 System
560.3
70%
74% √
Conventional Facilities
247.5
90%
93% √
Accelerator Systems
240.3
60%
65%√
Experimental Facilities
72.5
25%
31% √
5
BROOKHAVEN SCIENCE ASSOCIATES
User Workshops and LOIs
•Beamline & Strategic Planning workshops held Jan-Mar 2008
•Received 11 Letters of Interest (LOIs) from groups proposing
beamlines and wanting to form Beamline Advisory Teams (BATs)
•BATs work with facility to define scientific mission and technical
requirements for beamline during design, construction, and
commissioning of beamline
Experimental Facilities
Advisory Committee (EFAC)
•LOIs reviewed