Cisco-Training.net
1. Refer to the exhibit. A pre-sales system engineer receives a diagram of the current
network WAN connectivity from a customer. EIGRP is the routing protocol used on the
WAN. Based on the default operation of EIGRP, which statement is true about the
routing table on router R1?
There is a single route to the 192.168.16.0/28 LAN via the use of the T1 connection.
There is a single route to the 192.168.16.0/28 LAN via the use of the DSL connection.
There is a single route to the 192.168.16.0/28 LAN via the use of the Metro Ethernet
connection.
EIGRP installs all three routes to the 192.168.16.0/28 LAN and load balances the traffic.
2. A new host needs to be connected to VLAN 1. Router RA is attached to the VTP trunk
and configured as shown in the output contained in the graphic. Which of the following
IP addresses should be assigned to this new host?
192.168.1.1 /26
192.168.1.11 /28
192.168.1.22 /28
192.168.1.33 /28
192.168.1.44 /28
192.168.1.55 /28
3. Refer to the exhibit. A NetworkingCompany designer is reviewing a diagram of a
customer network. What two risks or issues can be identified in the topology that is
shown? (Choose two.)
The firewall router and ISP connection represent a single point of failure.
A failure of the switch that connects the Cisco Call Manager to the network will cause the
entire IP telephony system to fail.
Using Layer 3 switches to interconnect the data center servers to the IP phones introduces too
much delay.
The IP phones need to be redundantly connected to the switches to prevent single points of
failure at the access layer.
If one of the Layer 3 switches fails, the Cisco Call Manager will be unreachable.
Cisco-Training.net
4. An engineer who is part of a sales team has been asked to select technologies and
equipment capabilities to meet the network requirements of the prospective client. The
engineer is also responsible for diagramming the placement and interconnection of
various n