WATER & INFRASTRUCTURE COMMITTEE
MEETING MINUTES
SPECIAL MEETING AGENDA
NOVEMBER 6, 2006
7:30 PM
I.
Call to Order and Roll Call
Chairman called the meeting to order at 7:48pm. A quorum was present.
Greg Gehrke, Chairman
Tony Mancini
Keith Hunt, Mayor
Lee Fell, CBBEL
Jim Krischke, Village Administrator
Chris Burke, Village Engineer – CBBEL
Cliff Wright, Trustee Liaison arrived at 8pm
II.
Opportunity for the Public to Address the Committee
None.
III.
New Business
A.
None this month
IV.
Old Business
Chairman Gehrke opened the meeting and announced that the purpose of the meeting was to
review the progress of various issues with regards to the Toll Brothers Development. He said
that the agenda would be followed and Toll Brothers would be encouraged to provide their
input. Representing Toll Brothers were, Andy Stern, Tim Klinger, Patrick Tahaney, Keith
Hairrell, Hal Francke, H.H. Holmes representative and TSC representative.
A.
Schwerman Road
i. Nicor/Utility Relocation Update
CBBEL reported that NICOR was on-site relocating utilities and asked if the
work would still be completed on November 8th as promised.
Tim Klinger, Toll Brothers, said that work began on November 2nd and they
were working west and that all NICOR work would be completed by
November 10th.
Comcast work was already completed. All remaining utility work is outside
the paving area and will be completed in a timely manner.
Mayor Hunt questioned when the paving would be started and when can the
village anticipate it being completed. He addition he questioned when the
curbing would be done.
Andy Stern, Toll Brothers, said that curbing work was being worked on and
the majority of the curbing work would begin on November 8th on the East
end of Schwerman Road with completion set for November 13th. The work
on the west end would begin the week of November 20th. Paving to follow
curbing. Roundabout curbing to begin on November 7th.
Mayor Hunt and Village Engineer Chris Burke