Legend
A
4d
D
3d
Start
H
3d
B
7d
E
5d
F
4d
End
I
6d
Network Diagram with Finish-to-Finish Relationship
Finish
-to-
Finish
C
5d
G
6d
Name
Duration
ES
EF
LF
LS
Activity
FF
TF
ES = Early Start
EF = Early Finish
LS = Late Start
LF = Late Finish
FF = Free Float
TF = Total Float
d = days
PMP Certification Blog: http://www.deepfriedbrainpmp.com