PeopleSoft 9.0 Upgrade Schedule
Project Lead: David Wallace
Updated on: 2/20/2008
Today's Date: 2/25/2008
(vertical red line)
Project Start Date: 1/7/2008
Task#
Tasks
Resources
Start
End
Status
1 Install Demo 9.0 Instance for development use
iCIT
1/14/08
2/29/08
In Progress
2 Create a list of Active Customizations by functional
area
iCIT
2/1/08
2/29/08
In Progress
3 Create Test Plans identify functionality gaps in
delivered functionality vs. business processes
Functional
Offices
2/1/08
5/16/08
In Progress
4 Identify table changes between Peoplesoft 8.9 and
9.0 databases
iCIT
2/13/08
4/1/08
In Progress
5 Install UWW data without customizations to 9.0
development system
iCIT
3/3/08
4/1/08
6 Install approved customizations to 9.0 development
system
iCIT
4/2/08
5/9/08
7 User review of 9.0 with UWW data. Justify needed
customizations.
Functional
Offices
4/14/08
8/29/08
8 Analyze customizations to be carried forward into 9.0
production
iCIT
5/1/08
9/19/08
9 Determine customization priorities with
Customers/Governance Group/PM
Functional
Offices
9/3/08
10/31/08
10 PS Governance Team assesses overall project status
and recommends Go/No Go
PS
Governance
10/31/08
10/31/08
11 SOFT FREEZE--Version 8.9--Patches are still applied to
8.9; only critical items addressed
11/3/08
11/3/08
12 Developers apply approved customizations
development version
iCIT
11/3/08
3/17/09
13 Functional user testing of UWW approved
customizations
Functional
Offices
11/3/08
3/17/09
15 HARD FREEZE--Version 8.9--No Additional
Customizations/Patches
3/16/09
3/16/09
14 PS Governance Team assesses overall project status
and recommends Go/No Go
PS
Governance
3/17/09
3/17/09
16 Upgrade Prod 8.9 with P-Tool Upgrades for all
subsequent 9.0 Upgrades
iCIT
3/16/09
4/17/09
17 Assess test results, identify critical work to be done
for go-live
Functional
Offices
3/17/09
3/25/09
18 Developers apply critical day-one customizations to
9.0 system
iCIT
3/17/09
4/13/09
19 Developers continue applying customizations