1. You are managing a project schedule in Microsoft Office Project Standard 2007. You create 100 new tasks in the
project plan. Each task has a duration of 5 days, which you indicate by entering 5 in the Duration field. After every
third task you create, Project displays a message about an alternative method of setting the task duration.
You need to stop the message from appearing.
What are two possible ways to achieve this goal? (Each correct answer presents a complete solution. Choose two.)
A. Turn off the Project Guide.
B. In the message box, select the Don't tell me about this again check box.
C. In the general program options, disable the feature that provides advice about scheduling.
D. In the general program options, disable the feature that provides advice about using Project.
Answer: BD
2. You are managing a project in Microsoft Office Project Standard 2007. You will be managing similar projects in the
future, and plan to reuse information from the current project.
You need to save the tasks, durations, views, and formatting of the current project for reuse.
What should you do?
A. Save the project as a template.
B. Create a baseline of the project schedule.
C. Copy the project's rows from the Gantt Chart view into another project file.
D. Use the Organizer to transfer the information you want to save from your project into the Global.mpt file.
Answer: A
3. In Microsoft Office Project Standard 2007, you create a task that includes 80 hours of work and has a duration of
10 days. You assign one resource at 100 percent with a standard rate of $100 per hour, resulting in an actual cost of
$8,000.
You set the baseline. You set the status