University of Houston
Air Conditioning Cooling Load, Present and Future
Facility
Type of Building
Size
(GSF)
Diversified Cooling
Load Contribution
(tons)
Existing Buildings
12,700
Future Buildings:
Calhoun Lofts
Residence Hall
569,000
1,000
Cemo Hall
Classroom
339,000
800
Freshmen Housing-Phase 1
Residence Hall
339,000
600
Freshmen Housing-Phase 2
Residence Hall
339,000
600
Fleming Hall Addition
Classlabs/Research Labs
60,000
300
SERC Buildout
xisting
ell Space)
Research Labs
,
Stadium Addition*
Stadium Suites/classrooms
133,700
300
Bauer 3
Classrooms/Offices
87,000
200
EN Student Services
Classrooms/Offices
102,000
250
Valenti Addition
Classrooms/Studios
10,000
25
Optometry*
Classrooms/
Research Labs/ Clinics
137,000
700
TOTAL
17,725
Cooling Capacity of Utility Plant:
Existing Firm Capacity
14,000 tons
Proposed Firm Capacity
18,500 tons
Existing Total Capacity
19,000 tons
Proposed Total Capacity
23,500 tons
* Project may not be fed by Central Plant